‘30 pc PCMC-Shivajinagar metro work over’

ST CORRESPONDENT

PUNE: Mahametro officials on Friday said work of metro project on PCMC-Shivajinagar corridor has reached 30 per cent.

This was revealed by Chief Project Manager Gautam Birhade of Mahametro. 

“Around 110 pillars of the proposed 400 on PCMC-Shivajinagar corridor has been erected. Similarly work of 150 foundations has been done. The work on stations has started in Sant Tukaram Nagar, Kasarwadi, Phugewadi and Dapodi,” added Birhade. 

The metro project from Shivajinagar to Swargate will be divided into two parts, Shivajinagar to Budhwar Peth and from Budhwar Peth to Swargate. “While Swargate will be a multimodal hub a similar integration with other transport utilities will be required at Shivajinagar. The Shivajinagar metro station will be integrated with Shivajinagar railway station, PMT bus stand and state transport stand,” Birhade further added. From Vanaaz to Civil Court stations the Mahametro has laid 77 foundations and erected 14 pillars. 

The Mahametro will be building an information centre in the city for solving queries of people. “Currently there is one information centre for PCMC-Shivajinagar corridor. We will be shifting the centre in city,” added Birhade.

Enjoyed reading The Bridge Chronicle?
Your support motivates us to do better. Follow us on Facebook, Instagram, Twitter and Whatsapp to stay updated with the latest stories.
You can also read on the go with our Android and iOS mobile app.

Punawale: Husband Accused of Instructing Friends to Sexually Assault Wife

Phugewadi School Employee Accused of Harassment and Stalking Minor Girls

Cybercriminals Cheat Pune Residents of ₹3.35 Crore in a Day; Nine Cases Registered

Bomb Hoax on IndiGo Flight Causes Panic; Authorities Confirm False Alarm

Eminent Sanskrit Scholar Pandit Vasantrao Gadgil Passes Away at 95

SCROLL FOR NEXT